女人张开腿让男桶喷水高潮_国内精品免费一区二区2001_日韩综合在线播放_麻豆在网站1区_欧美日韩在线视频首页_天天狠天天天天透在线

sales@zmscable.com

What is the difference between pipe fiber optic cable and direct buried fiber optic cable?

1 year ago 1263 0 News

1689322362945691.jpg


Introduction to the difference between pipe fiber optic cables and direct buried fiber optic cables

We often talk about the concept of fiber optic cable, but in fact, many friends do not know much about the detailed knowledge of fiber optic cable. For example, what is the pipe fiber optic cable and direct buried cable, or what is the difference between pipe fiber optic cable and direct buried cable? The following ZMS cable editorial takes you to understand.

 

Definition of pipe fiber optic cable and direct buried fiber optic cable

Ducted Fiber Optic Cable

Pipeline cable is used in the access network or user premises network from the outdoor fiber optic cable, which is a communication cable laying method.

Pipe laying is generally in urban areas, pipe laying environment is better, so there are no special requirements for cable sheathing, and no need for armor.

Pipe laying must be selected before laying the length of the section and the location of the connection point.

Laying can be used for mechanical side traction or manual traction.

The traction force of one traction should not exceed the allowable tension of the fiber optic cable.

The material for making the pipe can be concrete, asbestos cement, steel pipe, plastic pipe, and so on according to geography.

Directly Buried Fiber Optic Cable

Directly buried fiber optic cable is a kind of communication cable laying method.

This kind of fiber optic cable is armored with a steel belt or steel wire outside and buried directly in the ground, which is required to have the performance of resisting external mechanical damage and preventing the performance of soil corrosion.

Difference between pipe fiber optic cable and direct buried fiber optic cable

Pipeline Cable

Pipeline fiber optic cable laying should make the following preparations:

1) According to the design of the fiber optic cable occupied by the position of the pipe hole.

2) In the same route the choice of the hole should not change, such as changes or bends, and should meet the requirements of the cable bending radius.

3) Each manhole should be manned when manually placing the fiber optic cable; the manhole should be manned when mechanically placing the fiber optic cable around the bend.

(4) When the fiber optic cable penetrates the pipe hole or pipe bends or crosses, it should be protected by a guide device or a flared protection pipe, and the outer protective layer of the fiber optic cable shall not be damaged.

(5) Neutral lubricant can be applied around the fiber optic cable as needed.

(6) The length of the fiber optic cable traction is generally not greater than 1000 meters. When the length is longer, it should take 8 segmented traction or the middle with auxiliary traction.

(7) Cable deployment, should be directed by a person unified, manhole by manhole will be placed in the provisions of the fiber optic cable on the pallet and should leave an appropriate margin to avoid the fiber optic cable being too tight.

(8) Joints where the manhole cable length should be reserved under the provisions of the table; design requirements for special reserve cable taut.

Pipeline cable protection measures should meet the following requirements:

1) Manhole in the fiber optic cable can be serpentine hose (or soft plastic tube) protected and tied in the cable tray or according to the design requirements of the measures to deal with.

2) The pipe opening should take plugging measures.

3) The fiber optic cable in the manhole should have an identification mark.

4) Cold areas should take anti-freezing measures according to the design requirements to prevent damage to the fiber optic cable.

The plastic sub-pipe deployment method is the same as the fiber optic cable deployment, and should also meet the following requirements:

1) When placing more than two sub-pipes without color marking, the marking should be done at the end.

2) The ambient temperature of the plastic sub-pipe should be between -5oC and +35oC.

3) The length of the continuously laid plastic sub-pipe should not exceed 300 meters.

4) The maximum pulling force of the sub-pipe should not exceed the tensile strength of the pipe, and the pulling speed should be uniform.

5) The remaining length of the sub-pipe in the manhole should meet the design requirements.

6) The pipe holes for wearing and placing plastic sub-pipes should be installed with plastic pipe plugs (other methods can also be used) to fix the sub-pipes.

7) The sub-pipe shall not have joints in the middle of the pipe.

8) Sub-pipe deployment is completed, the pipe opening should be made temporary plugging; this project does not use the sub-pipe must be installed at the end of the pipe plug (cap).

Direct Burial Fiber Optic Cable Laying

Directly buried fiber optic cable and other buildings and underground pipeline distance should meet the specified requirements.

The same ditch laying of fiber optic cables, shall not cross, or overlap, it is appropriate to use separate traction at the same time as the deployment of the way.

Direct burial fiber optic cable laying should meet the following requirements:

1) The depth of the fiber optic cable ditch should be under the provisions of the bottom of the ditch should be flat without gravel; the stony, semi-stony ditch bottom should be paved with 10 cm thick fine soil or sand.

2) When mechanically pulling, a ground pulley should be used.

3) When manually lifting and placing, the fiber optic cable should not appear less than the specified radius of curvature of the bend, as well as dragging the ground, hauling too tight, and other phenomena.

4) The fiber optic cable must be placed in the bottom of the trench, and shall not be vacated and arched.

5 Cable laying in the slope is greater than 20 °, the slope is greater than 30 meters on the slope, it is appropriate to use the "S" shape laying or according to the design requirements of the measures to deal with.

6) Deployment process or after deployment, should be a timely inspection of the cable sheath, if damaged should be repaired immediately; directly buried cable should be checked after laying the cable sheath to ground insulation resistance.

7) Fiber optic cable and copper conductors must be checked to confirm compliance with quality acceptance standards, before the whole ditch is back to the soil.

Optical cable trench backfill should meet the following requirements:

1) First backfill 15 cm thick crushed soil or fine soil, it is strictly prohibited to push stones, bricks, frozen soil, etc. into the ditch, and should be artificially stepped on.

2) The backfill should be 10 centimeters above the ground.

 

Above is what are the pipeline cable and direct burial cable and pipeline cable and direct burial cable difference between what all the content, I believe that after reading this article for the pipeline cable and direct burial cable have a certain understanding, I hope to give you help.






INQUIRY
主站蜘蛛池模板: 国内精品久久久久久久影视麻生 | 色94色欧美sute亚洲线路二 | 国产精品中文字幕一区 | 久久99精品国产麻豆婷婷洗澡 | 天天摸天天操天天干 | 国产产在线精品亚洲AAVV | 国产欧美一区二区三区精品酒店 | 日本熟妇无码色视频在线观看 | 久久久久久久国产免费看 | 国产+日韩+欧美 | 男人扒开女人腿桶到爽免费 | 日韩av一级片| 91九色精品 | 91精品老司机久久一区啪 | 久久精品人人 | 绯色av一区二区三区免费看 | 男人狂桶女人出白浆免费视频 | 中文精品一卡2卡3卡4卡国色 | av色站| av大全免费 | 一区二区三区香蕉视频 | www日本视频 | 中文字幕在线观看视频免费 | 少妇仑乱A毛片无码 | 日韩欧美一区二区三区 | 国产美女网址 | 亚洲免费高清 | 国产边打电话边被躁视频 | 亚洲高清国产拍精品动图 | 日韩av一区二区在线观看 | 免费成人黄色 | 欧美日韓性视頻在線 | 亚洲不卡一区二区三区 | 美女亚洲一区 | 天天爽夜夜爽视频 | 高清欧美性猛交xxxx | 一本大道香一蕉久 | 久久久久久久午夜 | 欧美精品第一区 | 国产又粗又猛又爽的免费网站 | 日本人妻丰满熟妇久久久久久 |